Stormwater Improvements & Bank Stabilization Projects

Lee's Summit, MO

Stormwater Improvements & Bank Stabilization Projects

Background

Lee’s Summit had several projects that required stabilizing road side slopes, channels, creek banks, a streambank threatening a nearby home, and designing new stormwater pipes and inlets.

Stormwater Improvements & Bank Stabilization Projects

Activity

Allgeier Martin was selected for five projects. The following four projects involved improving stormwater facilities, erosion control, and stabilizing streambanks:

  • NE Douglas Street at Municipal Airport
  • NE Bristol Drive
  • SE 2nd Street
  • SW 3rd Street

Technical Design & Features

  • 541 LF of 12-53” RCP/HDPP stormwater pipe
  • 466 channel-lining concrete blocks
  • 1,623 sq yd type 3 rock/riprap
  • 385 sq yd concrete stilling basin
  • 238 sq yd 4” thick concrete sidewalk
  • Fencing
  • Guardrail
  • Curb & gutter
  • Pre-cast curb inlets
  • Traffic control
  • Designed and delivered on time