Background

A city in central Oklahoma required a new electrical power source to support increased load from newly constructed schools on its east side. Allgeier Martin designed a 69 kV distribution substation that taps a new transmission line supplied by the regional utility. The substation enters service with four 25 kV distribution feeders and accommodates four future feeders, giving the city a reliable backbone for current demand and planned growth.

New Substation

Activity

Technical Design & Features

  • 160′ × 160′ security-fenced site with drive-through access
  • 69 kV high-bay single-bay structure, with foundations in place for expansion to four bays
  • 25 kV low-bay structure with eight bays and space for four additional bays
  • New concrete control building
  • Design: Oct 2021 – Aug 2022
  • Construction: Jan 2023 – Nov 2023