New 161kV Transmission Line Right-of-Way

Northeast Arkansas

New 161kV Transmission Line Right-of-Way

Background

For a new 6-mile 161 kV transmission line between two substations in Northeast Arkansas, Allgeier Martin’s right-of-way team secured 38 parcel easements from 24 landowners. The easement acquisition process took approximately six months to complete.

New 161kV Transmission Line Right-of-Way

Activity

Technical Design & Features

  • Secured 38 parcel easements from 24 landowners
  • Approximately 6 months to complete easement acquisition